Kitchen ceiling and floor materials removed from an apartment unit before new cabinets
Example project
- Home
- Ground-floor unit in a 1960s six-unit apartment building in Gardena, with a textured kitchen ceiling and sheet vinyl
- Original request
- The building owner is putting in new cabinets and a new floor while the unit is empty
- Testing
- A Cal/OSHA-certified asbestos consultant samples the ceiling texture, the sheet vinyl and its backing, and the wall compound
- Found
- Asbestos in the ceiling texture and the vinyl backing
- Clear
- The wall compound
- Area
- About 140 sq ft of ceiling and 110 sq ft of floor
- Timeline
- Notice no later than 10 working days ahead, then three working days
- Cost
- $4,400
Scope of work
Samples of each material, the district notice, the kitchen sealed with air filters running, the ceiling texture and the vinyl removed wet, bagging and the haul. The clearance air test, the cabinets and the new floor are separate.
Project overview
In this example, the owner of a small apartment building in Gardena is remodeling one ground-floor kitchen between tenants. A unit in an apartment building is not a residential single-unit dwelling, so the survey comes first whatever the size of the job.
The ceiling texture and the vinyl backing test positive, and the wall compound is clear. The abatement crew takes out both materials while the unit is empty, and the cabinet installer works in a clean kitchen.
The goal
The goal is a kitchen with the positive ceiling and floor materials gone before the remodel crew arrives.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the ceiling, the floor layers and the walls.
- Before work The abatement contractor files the district notice online, and the unit stays empty.
- Days one to three The kitchen is sealed, the texture comes down wet and the vinyl is lifted and bagged.
- Last An independent consultant tests the air, and the cabinet crew starts.
Planning right
- Keep the unit empty until the air results are in.
- Tell the neighbors upstairs when the crew will be on site.
- Hold the cabinet delivery for after the air test.
- Keep the lab report with your project papers.